(AP Photo/Vermont Yankee Corporation)
Friday October 19, 2012

BRATTLEBORO -- Test results from a drinking water well at Vermont Yankee mean the nuclear power plant's response to the discovery in January 2010 of a leak of tritiated is officially over, said a Yankee spokesman.

"As far as we are concerned, this is the end," said Jim Sinclair, manager of communications.

On Sept. 17, Yankee technicians sampled a decommissioned drinking water well connected to the plant's construction office building (COB). Samples were analyzed by both the Vermont Department of Health and a laboratory contracted by Yankee.

"Test results from both the Health Department Laboratory and its contract laboratory report that neither tritium nor gamma-emitting radioactive materials were detected in the COB well samples," stated a press release from DOH. "Tritium results ... were all less than the detection limit for all three samples."

The detection limits reported were between 511-530 picocuries per liter for tritium.

DOH is in the process of testing for hard-to-detect radionuclides such as iron-55, nickel-63 and strontium-90.

"We should get those in the next few weeks," said Bill Irwin, radiological health chief for DOH.

On Jan. 7, 2010, Yankee representatives notified DOH that a sample taken from a ground water monitoring well contained tritium. The finding signaled an unintended release of radioactive material.

The source of the leak was found a little more than a month later, but not


Advertisement

before samples revealed contamination at more than 500,000 picocuries per liter.

The EPA standard for drinking water is no more than 20,000 picocuries. No tritium was ever detected in drinking water wells either on or offsite.

Entergy, which owns and operates Yankee, mitigated the leak by withdrawing contaminated water from the ground and cleaning it up before putting it back into the plant's cooling system. Some of the contaminants were shipped off site to a disposal facility.

In October 2010, tritium contamination was found in the COB water well, a little more than 1,000 picocuries at 200 feet deep. At 300 feet there was no tritium above detectable level. The well had been taken out of service in March 2010.

In August 2011, tritium levels just above the lowest limits of detection were discovered in the Connecticut River, which was consistent with hydrogeological modeling that showed the contaminated plume flowing toward the river.

In April 2011, the state and Entergy began wrangling over whether the COB well should be tested again.

"We've always wanted to get these sample results because we hoped it would be verification that well water in the bedrock was protected," said Irwin.

"Vermont Yankee attempted to sample the well in September 2010 during a procedure called packer testing, but stopped when tritium was found in the well. They tried again in February 2011, but stopped when pumping appeared likely to draw water down from the tritium-contaminated groundwater above the bedrock," stated an update posted on DOH's website in April 2011. "Yankee officials have concluded that sampling the COB well cannot be done without risking contamination."

Entergy finally relented after receiving pressure from both the state and the Nuclear Regulatory Commission.

"We urged the company to check the COB well -- as did the state -- to check for any contamination at this lower elevation, and the company ultimately agreed to do so," said Neil Sheehan, spokesman for the Nuclear Regulatory Commission.

The most recent results are what Entergy expected, said Sinclair.

"Based on what we knew, we were confident there had been no migration of tritiated water down to the bedrock," he said, adding "We have no plans to do additional testing."

Yankee's normal groundwater monitoring will continue, said Sinclair.

"We will evaluate what we will do with the COB well," he said.

Bob Audette can be reached at raudette@reformer.com, or at 802-254-2311, ext. 160. Follow Bob on Twitter @audette.reformer.