BRATTLEBORO -- The Bridge 9 arched columns at Pier 1 adjacent to Route 30 are currently being constructed and are scheduled for completion this summer. Pier 2 foundations are nearing completion. The Pier 2 arched columns will be constructed this summer into fall.

Night work on the new bridge will continue at the columns on Route 30. Night work will occur Monday, Aug. 25, thru Friday, Aug. 29.

The Bridge 9 superstructure construction will begin at the end of the summer and continue for the next two years.

The new roadway alignment construction began last month. This work will be performed during the 2014 and 2015 non-winter seasons.

Northbound I-91 traffic has been relocated onto the southbound bridge. Traffic will remain reduced to one lane in each direction on I-91 until completion of the new bridge.

The new bridge will be 104-feet wide and is designed to carry all four lanes of traffic, two northbound and two southbound.

The speed limit on Route 30 near the work zone has been reduced to 40 mph. This reduction will remain in effect through the Spring of 2016.

Project-related truck activity on Route 30 will continue. Route 30 will be reduced to a single lane intermittently both day and night, with flaggers regulating traffic within the work zone.

No project-related impacts to Upper Dummerston Road are anticipated for the week of Aug. 24.

The West River Trail is now open.


Advertisement

There are intersections between construction access and the trail path, and users should exercise extreme caution at these intersections. As an additional safety precaution, users of the West River Trail are reminded to keep pets on a leash in this area.

The northbound bridge over the West River has been removed. No project-related impacts to recreational boaters are anticipated for the week of Aug. 24.