BRATTLEBORO — DMI Paving, a contractor of the town, will begin the paving portion of Brattleboro's annual capital paving project. Weather permitting, the following schedule is anticipated:

Monday, September 14

- BPD Driveway - Shim and pave the driveway into the police department.

- Preston Parking Lot - Preparation and shim work. The parking lot will be closed to parking. Seek alternate parking locations.

Tuesday, September 15

- Preston Parking Lot - Final Paving. The parking lot will be closed to parking. Seek alternate parking locations.

Wednesday, September 16

- Chestnut Hill Extension - Preparation and paving. The street will be closed to through traffic during paving operations, and driveway access may be limited. Each street closure may take several hours.

- Chestnut Hill Loop - Preparation and shim work. The street will be closed to through traffic during paving operations, and driveway access may be limited. Each street closure may take several hours.

Thursday, September 17

- Chestnut Hill Loop - Final paving

- Acorn Lane - Final Paving. The street will be closed to through traffic during paving operations, and driveway access may be limited. Each street closure may take several hours.

Friday, September 18

- Rain date/final paving as needed.

Work is expected to happen between 7 a.m. and 5 p.m. On-street parking will not be permitted during paving operations. No parking signs will be posted the afternoon prior to work on each street. For more information contact Dan Tyler, Highway and Utilities Superintendent at 802-254 - 4255 or dtyler@brattleboro.org .